Construction money, explained
AIA billing (G702 & G703)
AIA billing is a standardized way to request construction progress payments using two American Institute of Architects forms — the G702 Application and Certificate for Payment (the summary cover sheet) and the G703 Continuation Sheet (the line-item detail) — that work together as one pay application.
Updated June 2026
What is AIA billing?
AIA billing is the most widely recognized format for progress payments on commercial and institutional construction. It standardizes how a contractor requests payment so owners, architects, and lenders can review every project the same way. The package is built on two forms from the American Institute of Architects that are nearly always used as a pair.
The G702, the Application and Certificate for Payment, is the one-page summary: original contract sum, change orders, total completed and stored to date, retainage, previous payments, and the current payment due. It also carries the contractor's certification and a block for the architect to certify the amount. The G703, the Continuation Sheet, is the detailed backup — the schedule of values, line by line.
How do the G702 and G703 work together?
You fill out the G703 first. Each line of the schedule of values shows its scheduled value, work completed in previous applications, work completed this period, materials presently stored, total completed and stored to date, the percent that represents, the balance to finish, and the retainage on that line. The columns total at the bottom.
Those totals roll up into the G702 summary. The 'total completed and stored to date' on the G702 must equal the corresponding total on the G703 — that reconciliation is what makes the application internally consistent. The G702 then subtracts retainage and prior payments to arrive at the current payment due.
The architect reviews the application, may adjust the certified amount, signs the certificate, and the owner pays based on that certification. This review-and-certify loop is the core of why AIA forms exist: an independent party confirms the work before money is released.
How do you fill out AIA billing forms?
Set up the schedule of values once at the start, with line items that sum to the contract sum. Each period, update the work-completed and stored-materials columns, fold approved change orders into the contract sum on the G702, and let the retainage column compute the held amount. Reconcile the G703 totals to the G702 before submitting.
Accuracy matters because a mismatched or over-billed application gets kicked back, delaying payment. Common snags are forgetting to carry change orders into the contract sum, front-loading early line items, and retainage that doesn't tie out across the two forms.
Simple Contractor CRM doesn't generate the official AIA forms today, but the structure it produces maps cleanly onto them: a line-item estimate becomes the schedule of values, progress draws track work completed by period, and retainage is applied per draw. That gives you the same underlying numbers a G702/G703 needs. Native AIA-format export is the kind of capability that would be on the roadmap, not something to claim today.
Worked example
On a $500,000 contract with 5% retainage, suppose the G703 shows $200,000 of work completed and stored to date across all line items. The G702 summary carries that same $200,000 forward as 'total completed and stored to date.'
Retainage at 5% is $10,000, leaving $190,000 earned net of retention. If previous certificates already paid $120,000, the current payment due on this application is $190,000 minus $120,000, or $70,000 — the figure the architect certifies and the owner pays.
Frequently asked
- What is the difference between the G702 and G703?
- The G702 is the one-page summary and certificate that states the current payment due; the G703 is the continuation sheet that breaks the contract into the line-item schedule of values supporting that summary.
- Are AIA forms required by law?
- No. They are copyrighted industry-standard documents from the American Institute of Architects, widely required by contract on commercial work, but not a legal mandate. Many private jobs use simpler pay applications.
- Who certifies an AIA pay application?
- The contractor signs the application, and the architect (or owner's representative) reviews and certifies the amount before the owner releases payment.
- Does the G703 show retainage?
- Yes. The continuation sheet includes a retainage column per line item, and that retainage flows up into the G702 summary, which subtracts it to compute the current payment due.
Run the next job the simple way.
Join early access and lock in founding pricing.